With the arrival of spring, Broome County drivers once again might do well to stay away from where the $25 million Greenway project is being constructed.

Construction on the 2.5-mile-long pathway for pedestrians and bicyclists along the Vestal Parkway has resumed after a three-month winter break.

Drivers encountered lane closures in the Greenway construction area on March 20, 2023. Photo: Bob Joseph/WNBF News
Drivers encountered lane closures in the Greenway construction area on March 20, 2023. (Photo: Bob Joseph/WNBF News)
loading...

Motorists making the usually-quick trip between downtown Binghamton to the Vestal town line Monday discovered the Parkway was more like a parking lot. A typical two-minute ride turned into a 22-minute scenic journey next to the Susquehanna River.

Westbound traffic crawled and at times came to a standstill as drivers approached the active work zone near University Plaza. The backup was caused by the closure of the right lane. Motorists then encountered a left-lane closure for a signal installation project.

Traffic heading from downtown Binghamton to Vestal came to a halt due to lane closures in the Greenway work zone. Photo: Bob Joseph/WNBF News
Traffic heading from downtown Binghamton to Vestal came to a halt due to lane closures in the Greenway work zone. (Photo: Bob Joseph/WNBF News)
loading...

According to the state Department of Transportation, the grading and paving of the pathway is planned in the coming weeks. Lighting work will be completed along the Greenway route.

Crews will be finishing work on a retaining wall near Clubhouse Road. They'll also be installing call boxes, bicycle railings and fencing.

Workers in the Greenway construction zone in Vestal on March 20, 2023. (Photo: Bob Joseph/WNBF News)
Workers in the Greenway construction zone in Vestal on March 20, 2023. (Photo: Bob Joseph/WNBF News)
loading...

The DOT reports the estimated "substantial complete date" for the Greenway project is May 2.

The shared use pathway will run from Pennsylvania Avenue in Binghamton to Murray Hill Road in Vestal.

The current construction contract cost for the project is about $25.2 million. That's an increase of more than $3 million over the original contract award cost.

A sign protesting the 434 Greenway project in front of a Vestal Avenue residence on November 30, 2020. (Photo: Bob Joseph/WNBF News)
A sign protesting the 434 Greenway project in front of a Vestal Avenue residence on November 30, 2020. (Photo: Bob Joseph/WNBF News)
loading...
99.1 The Whale logo
Enter your number to get our free mobile app

Contact WNBF News reporter Bob Joseph: bob@wnbf.com or (607) 545-2250. For breaking news and updates on developing stories, follow @BinghamtonNow on Twitter.

LOOK: Route 66’s quirkiest and most wonderful attractions state by state

Stacker compiled a list of 50 attractions--state by state--to see along the drive, drawing on information from historic sites, news stories, Roadside America, and the National Park Service. Keep reading to discover where travelers can get their kicks on Route 66.

LOOK: Baby boomer baby names that have gone out of style

Using info from the Social Security Administration's baby name database, Stacker compiled a list of baby boomer baby names that have declined in popularity.

LOOK: 50 songs you won't believe are turning 50 this year

From classic rock anthems to disco hits and everything in between, Stacker surveyed Billboard's Hot 100 list of top songs in 1973 and highlighted the top 50.

More From 99.1 The Whale