It sure has been a busy season for road work and construction this year. There were times when it seemed getting from point A to point B was almost impossible, but these projects only make for a better future travel experience.

Some roads/streets around my neighborhood are much nicer now that they've received fresh paving for a smooth ride.

While many projects are complete, there are still some in progress. While I'm sure this is not a complete list, here are some areas to be aware of for your commute this fall.

Binghamton

Roadwork has begun on the Conklin Avenue Railroad Bridge near Sandy Beach Park.  A temporary traffic signal is in place, allowing one lane of traffic to remain open at a time. This work will include repaving, curb and sidewalk repairs, and fencing repairs, and is expected to take three weeks, weather permitting.

State Street North from the northbound side of the State Street Bridge to Susquehanna Street in the City of Binghamton reopened to traffic on Monday, October 26th. The roadway had been closed for construction as part of the Binghamton 363 Gateway Project, and is reopening one month ahead of schedule. Eastbound State Route 434 traffic, via State Street Bridge, remains reduced to one lane of traffic between the bridge and the ramp.

Vestal

Beginning Wednesday, October 28th, milling and paving operations will begin on Rodger Avenue between Route 434 and Walter L. Road and on Walter L. Road between Airborne Avenue and Brady Avenue. Residents may at times have limited access to their driveways.  Weather permitting, crews should complete the work within three to five days.

Route 17/I-86

Single-lane traffic between exits 67 and 69 for bridge work. Route 26 North ramp to Route 17/I-86 remains closed.

Broome County Highway Work (Final Week For The Season)

• Paving Saddlemire Road - County Route 125 (from Pennsylvania Ave to Pierce Creek
Road)
• Paving Pierce Creek Road – County Route 141 (from Saddlemire Road to Murphy Road)
• Cleaning ditches on Oakdale Road, Day Hollow Road, North Sanford Road & Old Route 17
• Culvert work on Old State Road, Sanitary Springs Road & Powderhouse Road
• Guide rail work on Bunn Hill Road
• Mowing the right-of-way on Broome County roadways

State Route 8 - Chenango County

Culvert replacement on State Route 8 between State Route 80 and County Route 25 in the Town of Columbus, Chenango County, will begin Monday, November 2, weather permitting.
Traffic will be reduced to a single lane with alternating one-way traffic controlled by temporary signals. State Route 8 will close to all traffic from the morning of Saturday, November 7, through early morning Monday, November 9, with a signed detour in place directing traffic to State Route 80 and County Route 25. After the closure, traffic will return to a single-lane configuration until the project is completed approximately two weeks later.

The Week That Was: In Photos (Oct. 22, 2026)

QUIZ: Can You Identify These Awesome '80s Movies From Just a Single Freeze-Frame?

From a stranded alien trying to phone home to a group of kids on a treasure hunt, see how many of these iconic ’80s blockbusters you can recognize from a single freeze frame.

Gallery Credit: Stephen Lenz

More From 99.1 The Whale